01 Technical availability
Could the equipment run?
Hours a unit was operational ÷ daylight hours in the period, per inverter, weighted by rated capacity. Operational means producing, in standby without a fault, or held down by a command: available is operational, not performing, so curtailment never lowers it. Nothing is excluded. A data gap is “unknown”: removed from numerator and denominator and reported beside the number as an unknown share, never counted as available.
02 Contractual availability
Did the O&M contractor deliver what was signed?
Same calculation, but the intervals on the contract's exclusion list are removed from numerator and denominator: grid outage, grid-operator curtailment, market curtailment, owner shutdown, force majeure, scheduled maintenance within the agreed quota. The number carries the contract reference.
03 Energy-based availability
What did downtime cost in energy?
1 − energy lost during unavailable intervals ÷ expected energy of the period. Expected energy per interval comes from measured irradiance and the plant's own reference performance, or from peer inverters when the sensor is out. Exclusions as in 02 when the contract ties damages to energy, otherwise none; the number says which.
04 Revenue-weighted availability
What did downtime cost in money?
As 03, but every lost kWh is valued at that interval's price, day-ahead or the price the owner actually receives. A lost kWh at a negative price is worth nothing. An hour lost at noon in June can cost nothing; an evening hour in January costs a lot. This is the number to tie liquidated damages to.
05 Energy performance index
Did the plant capture what was there?
Actual energy ÷ expected energy, with expected from irradiance, module temperature and dated master data. Everything counts: outages, curtailment, soiling, clipping, degradation, strings out. Not an availability, never called one.
06 Lost energy by cause
Where did the gap go?
Expected minus actual, split into grid outage, grid-ordered curtailment, market curtailment, export limit, clipping, unavailability, and underperformance as the remainder. The parts sum to the gap exactly.
07 Revenue capture ratio
Did we earn what the market offered?
Actual revenue ÷ (expected energy × interval price). For storage, against a named benchmark dispatch, and the benchmark is part of the definition.